starts on 12 September, 2018 ends on 26 September, 2018
Should the US vote to ratify the WE-OMC approval of LM Wind Power A/S as an RETL for Blade testing within the IECRE System (WE-OMC/311/DV)?
BACKGROUND:
On 2018-07-17 WE-OMC/311/DV was sent to WE-OMC Member Bodies who were requested to provide approval of LM Wind Power A/S as an RETL. The results of voting (WE-OMC/332/RV) were published on 2018-09-03. All of the WE-OMC Member Bodies voted in favour of LM Wind Power A/S to operate as RETL for Blade testing.
Therefore, in accordance with the approved WE-OMC transition plan, this is now being submitted for ratification to the REMC.
ACTION:
The REMC Member Bodies to ratify LM Wind Power A/S for RETL status, effective immediately. Ballots are to be returned to the IECRE Secretariat ([email protected]) no later than 2018-10-17.
NOTE: USNC/IECRE ballots to be submitted within two weeks to allow for resolution of any comments prior to the IEC deadline.